Fase do projeto

timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
Pending
Planning
Design
Construction
Complete
We are nearing the end of construction!

Informações do projeto

Location
Murphy Playground Jamaica Plain 02130
See all
Project Features
Accessibility
Community engagement
Demolition and construction
Green infrastructure
Infrastructure improvements
Landscaping
Playground
Sports fields and courts
Sustainability
See all
Ano de conclusão
2026
Project Manager
Nelle Ward
Consultant
CBA Group
Contractor
Fleming Brothers, Inc.
Primary Project Type
Parks and Green Space

Some of the fencing has become overgrown with vegetation. The walkways and seating are currently difficult to navigate in a wheelchair. The playing fields have depressions that can be hazardous for players and weeds popping up throughout.

Field improvements at Murphy Playground include:

  • renovations to improve the condition of the grass fields
  • provide new sports lighting (with less light leakage)
  • new pathways and new seating
  • renovated concrete bleachers
  • newly secured perimeter walls
  • repairs to the existing chain link fence and netting.

Special care will be given to preserve and improve the health of the existing trees. The Improvements aim to make the overall park more ADA Accessible.

The construction budget is $2,500,000.

We plan to wrap up general site construction fall 2025, but the athletic fields will remain offline until Spring 2026 while the grass establishes!

 

 